Launch of the 5-Year National Economic Development Plan in 1962 had made Daelim the leader of the construction industry in Korea in terms of the construction project volume by 1966. The Headquarters was moved to Seoul to begin the Seoul Age.
1963 03 Mr. Jae-jun Lee inaugurated as the CEO and President
1964 03.31 Constructed Yeongweol Thermoelectric Power Plant No.2
1965 11.25 Installed water turbines for Cheongpyeong Hydroelectric Power Plant No.2
1966 01.28 Made entry into Vietnam (Rach-Gia Port pile-driving project)
1966 04.19 Constructed the Gwanghwamun Underground Walkway
1967 12.31 Constructed the Ulsan Port Harbor No.1
1967 01.07 Constructed the Busan Thermoelectric Power Plant Unit # 3&4
1967 03.24 Constructed Gyeongin (Seoul-Incheon) Expressway
1968 02.01 Constructed Gyeongbu (Seoul-Busan) Expressway
1968 07.12 Constructed Donghae Thermoelectric Power Plant
1969 05.05 Constructed Namsan Children¡¯s Center
1969 05.08 Constructed Honam Thermoelectric Power Plant
1969 07.17 Constructed the National Assembly House
1971 02.22 Constructed Yeoeuido Square
1971 03.24 Constructed Yeongdong Expressway (Singal - Saemal: 13.6§°)
1971 04.12 Constructed Seoul Metropolitan Railway Line No.1